ACP Construction Schedule


Allegheny-Blue Ridge Alliance has prepared the list below indicating when (after receiving all certificates and permits) proposed construction on the Atlantic Coast Pipeline is scheduled to commence and end for those portions in West Virginia and Virginia (to the southern Buckingham County border). Each section, or spread, of the route is also detailed in a map that can be accessed here.

Each entry lists the spread mileposts, the location, and the start and end dates:

  • Spread 1-1 0.0 – 17.2 Harrison, Lewis (WV) 2019 4Q 2019
  • Spread 1-2 17.2 – 31.6 Lewis, Upshur (WV) 2019 4Q 2019
  • Spread 2-1 36.1 – 47.3 Upshur, Randolph (WV) 2018 4Q 2018
  • Spread 2-2 47.3 – 56.1 Randolph (WV) 2018 4Q 2018
  • Spread 2A 56.1 – 65.4 Randolph (WV) 2018 4Q 2018
  • Spread 3 65.4 – 79.2 Randolph, Pocahontas (WV) 2019 4Q 2019
  • Spread 3A 79.2 – 91.3 Pocahontas (WV), Highland (VA) 2018 4Q 2018
  • Spread 4 91.3 – 103.1 Highland, Bath (VA) 2019 4Q 2019
  • Spread 4A 103.1 – 125.9 Bath, Augusta (VA) 2018 4Q 2018
  • Spread 5 125.9 – 183.3 Augusta, Nelson (VA) 2019 4Q 2019
  • Spread 6 183.3 – 239.6 Nelson, Buckingham (VA) 2018 4Q 2018