DEQ Issues Stop Work on 2-Mile Section of MVP

Following is a statement issued by the Virginia Department of Environmental Quality on August 2, 2019.

Contact: Ann Regn, 804-698-4442, Ann.Regn@DEQ.Virginia.gov

DEQ ISSUES STOP WORK ON APPROXIMATELY TWO-MILE SECTION OF MOUNTAIN VALLEY PIPELINE

All ongoing clearing, grading and trenching must stop in this designated area

RICHMOND, Va. – The Virginia Department of Environmental Quality (DEQ) has issued a stop work instruction to Mountain Valley Pipeline, LLC (MVP). The instruction is based on issues identified during DEQ inspections that cite insufficient erosion and sediment controls on approximately a two-mile section of the project in Spread H in Montgomery County.

Based on a DEQ inspection conducted on Thursday, Aug. 1, the agency has determined that an imminent and substantial adverse impact to water quality is likely to occur as a result of land-disturbing activities. Specifically, MVP has failed to construct and maintain erosion and sediment control or pollution prevention measures in accordance with approved site-specific plans and/or the erosion and sediment control measures that have been installed are not functioning effectively and MVP has not proposed any corrective action.

Work in this section will be suspended until these corrective actions are installed and approved by DEQ through field inspection and verification. MVP must stop all land disturbing activities in this area including clearing, grading and trenching activities in the designated area. The only activity currently authorized in this area is work necessary to install and maintain erosion control devices as required by the approved site-specific erosion and sediment control plans, and the annual standards and specifications.

“We are appalled that construction priorities and deadline pressures would ever rise above the proper and appropriate use of erosion control measures,” said DEQ Director David Paylor. “DEQ will continue to monitor and inspect all ongoing work to ensure continued compliance and protection of Virginia’s natural resources.”

For more information and the full stop work instruction, visit www.DEQ.Virginia.gov/MVP

Press coverage in the Roanoke Times is here. The Roanoke Times article says, “Environmental advocate Russell Chisholm said in a release that he was ‘appalled’ that the company’s skimping on control measures to advance the project surprised the DEQ. Citizens have repeatedly reported similar lapses in permit compliance for at least a year.”    His statement noted that “In response to citizen reports, ‘those in positions of power chose to ignore our calls for real, meaningful enforcement through a stop work order and instead allowed MVP to work despite several missing federal permits, a pending lawsuit for violations, and at least 35 Notices of Violation in West Virginia.'”


An additional blow to MVP on August 2, 2019, came from federal district court Judge Elizabeth Dillon, who denied the pipeline company’s request for an order removing tree sitters on the route.  See Jonathan Sokolow’s report.