Request for Rehearing and Motion for Stay of FERC’s ACP Decision

Breaking news from the Allegheny-Blue Ridge Alliance (ABRA):

Late afternoon on November 13, 2017, a motion was filed with the Federal Energy Regulatory Commission (FERC) requesting a rehearing of the Commission’s order issuing a certificate for the Atlantic Coast Pipeline. The petition, filed on behalf of 22 organizations (including Friends of Nelson) and 10 individuals, requests that the Commission:

1. Grant Intervenors’ request for rehearing;

2. Grant Intervenors’ motion for a stay and immediately stay applicants and their contractors from taking any action authorized by the Certificate Order including, but not limited to, construction of the projects (including tree clearing) and any attempt to use the power of eminent domain pending final action on the request for rehearing;

3. Upon completion of the rehearing process, rescind the Certificate Order;

4. Grant Intervenors’ request for an evidentiary hearing concerning the market demand for the Atlantic Coast Pipeline;

5. Before making any new certificate ruling, conduct an analysis of whether the projects are required by the public convenience and necessity, as required under the NGA, that complies with the Commission’s Certificate Policy Statement;

6. Before making any new certificate ruling, conduct a NEPA analysis that addresses the direct, indirect, and cumulative impacts of the projects; provides a robust analysis of alternatives, including the existing infrastructure alternatives; and addresses the other NEPA-specific issues set forth in this request and Intervenors’ previous comments in these dockets.

7. Grant any and all other relief to which Intervenors are entitled.

A copy of the 210 page petition is available on the ABRA website, see https://www.abralliance.org/wp-content/uploads/2017/11/Petition_for_Rehearing_to_FERC_20171113.pdf.