We’ve killed the Atlantic Coast Pipeline, now it is time to kill the Mountain Valley Pipeline. Continue the fight! Join with some of the organizations fighting the MVP:
- POWHR (Protect Our Water, Heritage, Rights) Coalition – https://powhr.org
- Mountain Valley Watch – https://powhr.org/mvwatch/
- Appalachians Against Pipelines – https://www.facebook.com/appalachiansagainstpipelines/
- Water is Life…Protect It! – https://www.facebook.com/waterislifeprotectit/
- Allegheny Blue Ridge Alliance (ABRA) – https://www.abralliance.org
Two articles provide helpful background.
In his August 10, 2020 article, Despite company claims, only a fraction of the Mountain Valley Pipeline is complete in Virginia, Jonathan Sokolow writes, “”While substantial work appears to have been done in West Virginia, according to MVP’s own numbers they barely have gotten started in Virginia. The truth is that in Virginia MVP is less than 15 percent complete. That’s 15.75 miles complete in Virginia out of a total of 108 miles. …. It turns out MVP is, to be generous, manipulating numbers to create a false impression. It would be like a contractor telling you your new house is ‘almost complete’ because ‘most’ of the wood framing is ‘done’ even though you have no electricity, no water, no roof, no walls, no floors – and the contractor is missing multiple permits to do that work because they got sued in federal court – and lost.”
On September 2, 2020, a Virginia Mercury article points out that Despite rosy projections, all is not well with the Mountain Valley Pipeline. “Following the cancellation of the Atlantic Coast Pipeline, the developers of the Mountain Valley Pipeline have not been shy about talking up their own project in the Appalachian region. However, behind the rosy pronouncements of late, all is far from well with the MVP. …. MVP has requested the Federal Energy Regulatory Commission grant an extension of its construction timeline until Oct. 13, 2022. The reality is that MVP is over two years behind schedule and $2 billion over budget. Given federal permit suspensions, a nearly year-long — and counting — project-wide Stop Work order, ongoing legal challenges and ballooning financial woes, MVP cannot forecast when, or if, the project will be finished.”
Follow us on Facebook & Twitter: